When a customer asks for extra work, turn the conversation into a clear record of what changes, what it costs and what happens to the schedule. Use this checklist alongside your existing quote and contract.

What is a building variation?

A building variation is a change to the agreed work: an addition, an omission, or a change in materials, location or method. Adding a power point after the quote is accepted is a simple example. Replacing one specified finish with another is another. A variation may increase or reduce the price, and it may affect the completion date.

Start by comparing the request with the original scope. If the work is already included, clarify that before preparing an extra charge. This is a practical record-keeping guide, not a contract form or legal advice; check your contract and applicable requirements for the job.

02 — Worked example

From “add a couple of sockets” to a clear scope.

Illustrative example only. The figures are not a trade price recommendation.

Request and scope

The customer requests two additional white double power points on the study’s east wall, at positions marked on the attached photo. Supply, install and test the two outlets. These are additional to the outlets in the accepted quote.

Exclusions and assumptions

Painting and plaster repairs are excluded. The price assumes accessible cable routes and that the existing circuit is suitable. If inspection shows further work is needed, describe and price that separately for review.

Price change

Additional work: A$400 excluding GST. Credits: A$0. GST: A$40. Total increase: A$440 including GST. This example assumes the contractor is GST-registered.

Time and approval

Allow two additional working hours during the scheduled visit, with no proposed change to the completion date under these assumptions. Attach the marked-up photo and obtain the customer’s decision on this exact scope and amount before scheduling the extra work.

04 — After the decision

Keep the approval connected to the work.

If the customer approves

Save the agreed scope, attachments and approval together. Use the same variation reference when scheduling and preparing the invoice so the charge is easy to reconcile.

If the customer requests a change

Revise the scope, amount or timing and send the revised version for review. Retain the earlier version so the decision history remains understandable.

If there is no decision

Keep the variation marked as pending and follow up. Do not describe an unanswered request as an approval.